Set task due dates and due-date rules

Choose a specific date or calculate task dates from process events, project milestones, and other due dates.

Set a specific due date for a one-off deadline, or use a due-date rule when the deadline should follow a process event, project milestone, or another task's due date.

Before you begin: Use Editor or Administrator access for process setup and rule editing. Available controls depend on whether you are editing the reusable Playbook process or live project or operation work.

Set a specific date on live work

  1. Open the task in its project or operation.

  2. Select its due-date control, such as Add due date or the existing date.

  3. Choose a suggested date or use Choose date to pick one from the calendar.

  4. Confirm the displayed date changed.

Use Remove due date to clear a date where that option is offered.

Set a due-date rule

  1. Open the task's due-date control. In a reusable process, use Add due date rule; in a live process, choose Set rule where offered.

  2. Under Count from, choose Process event, Project milestone, or Another due date.

  3. Select the event, milestone, or task to count from.

  4. Choose Count days or Day of week, then enter the timing and the available Before or After choice.

  5. Review the non-working-day adjustment and select Save rule.

Choose what starts the calculation

  • Process event: calculate forward from the process activating or an eligible task being completed. A future event does not have a known date yet.

  • Project milestone: calculate from the milestone that opens the process's phase or the next milestone in the project's timeline. This requires project-phase context.

  • Another due date: calculate from an eligible task's due date. This can follow that task when its due date changes.

Subtrak excludes choices that would create a circular rule. If a choice is unavailable, read the explanation in the dialog.

Understand working days

Count days counts the company's working days and skips active company holidays. For example, two working days after a Friday event normally falls on Tuesday when the company works Monday through Friday and no holiday intervenes.

Day of week chooses the next or previous occurrence of the selected weekday relative to the anchor. Review the holiday adjustment rather than treating this as the same calculation as counting working days.

Understand waiting dates and later changes

A saved rule can wait until its event, milestone, or anchor date is known. A process can therefore have a rule without a calculated date yet.

A due-date rule determines when a task is due. It does not activate an On deck process or choose a decision answer. Review the resulting dates after changing milestones or manually choosing a date.